On 7 October the Federal Cabinet (Bundeskabinett) approved changes of draft bill amending various laws concerning power line extension. The draft bill inter alia gives priority to underground cables instead of overhead lines in case of new high-voltage, direct current transmission lines (HVDC).
Yesterday’s decision paves the way for a faster and supposedly more accepted grid expansion. This shall lead to more acceptance, as in many places residents raised major concerns against overhead lines, Federal Minister of Economics, Sigmar Gabriel said.
1. Priority of Underground Cabling for New HVDC Projects
The draft bill changes the provisions in the Act on the Federal Requirement Plan (Bundesbedarfsplangesetz – BBPlG). Draft Sec. 3 para 1 BBPlG gives priority to underground cables in case of HVDC projects. Close to residential areas overhead lines shall be in general not admissible (Draft Sec. 3 para 4 BBPlG).
These changes concern primarily the major north-south routes as SuedLink (South Link) or South East HVDC. Both lines – originally planned as overhead lines – have faced substantial protest of the public, especially in the Federal State of Bavaria. With the amendments pubic acceptance shall improve.
2. Extension of Pilot Projects for Three-Phase Electric Power Lines
In opposition to HVDC lines the DC cable projects retain their character as pilot projects. The reason for this difference is that the risks (technical risks and costs risks) of underground cable are lower for DC transmission. Furthermore less experience exists.
Nevertheless the pilot projects shall be extended. The draft bill lists four projects in the BBPlG where an installation of underground cables is admissible if certain criteria are fulfilled (e.g. short distance to residential buildings: less than 400m in case of a zoning plan, less than 200m in outside areas). The draft BBPlG stipulates that an installation of underground cables is also possible if the criteria for an installation are only fulfilled for a section of the entire power line.
3. Next Steps
The bill will now undergo the parliamentary process, including readings in the Bundestag. The aim is to conclude the discussions in autumn, so that the law can enter into force quickly and the necessary planning of the transmission lines can be started or continued swiftly.
I had to use Google Translate to translate the document into English from German, but, according to the legislation directly:
With the changes in the federal law requirements plan is for the planning and Construction of HVDC lines a priority of underground cabling in the Bundesfachpla- tion introduced. The broad acceptance of the citizens is a key element for the success of the energy turnaround. In particular, described the construction of HVDC lines There are special challenges. The increased use of underground cables can optionally contribute to the acceptance of these urgently needed Strengthening projects. From a technical point of view, between the AC and the DC area to distinguish. In the power transmission over long distances by means HVDC underground cabling has fewer risks in terms of technical implementation and the costs as a relatively underground cabling of rotation power lines over long distances. In addition, more experience is available with DC current underground cables over longer distances than with three-phase underground cables before.and:
In DC area, the existing principle that the route planning Overhead lines based vice versa. In HVDC lines underground cabling is the rule. In the vicinity of residential areas of the overhead line is even always un-admissible. This is the highest level of acceptance for this new Created DC lines.and:
§ 3 BBPlG - new - is the central norm, the prioritization of underground cabling will be implemented for the new HVDC lines.So, as a country, what are we going to do? Germany is already going through this. The people have spoken there, and they will continue to speak here: the status quo is unacceptable. The people will not be mowed over by a massive overhead HVDC transmission line in Germany that is necessary, and they most definitely will NOT be mowed over by a private LLC in the United States for a massive overhead HVDC transmission line that is absolutely NOT necessary.
Listen, I am a progressive. I don't get any money from the Koch brothers, and I sure don't think the Keystone Pipeline would be a fantastic addition to our country, but at least the states have the option of choosing whether or not to give eminent domain to TransCanada. I am in favor of renewable energy expansion, but it's going to have to be done properly. The technology exists to put things like this underground, despite what Clean Line tells you. One of the proposed transmission lines in Germany that caused this is a 500 mile, 500kV, 4,000mW HVDC line, the SuedLink. Sound familiar? Clean Line has only one reason they don't want to put it underground: return on investment for the executives and their billionaire investors.
But, you know what? I don't care about Clean Line's return on investment. What I care about is being treated with respect, my friends and neighbors being treated with respect, and I want to see our future infrastructure be built properly. There are going to be a lot of projects that come along. Some of them will be good ones, and some of them will be bad ones. Clean Line's projects, in my opinion, are bad ones, and they are being developed by, quite frankly, a few arrogant and potentially corrupt people. The people aren't going to accept that.
To any progressive lawmakers who may be reading this, or any others for that matter: If you want to get any of this kind of stuff done, you're going to have to start listening to the people. Bypassing state authority isn't going to do it, Senator Heinrich. The status quo is over. Social media will not allow the Clean Line model to work. It just won't. Take a lesson from the Germans who are a few years ahead of us.
Why are we all still here? I don't have an answer for you.